Building

Permits

Building permits and inspections help ensure that design and construction comply with the Ontario Building Code, providing safe and healthy environments in homes, workplaces and public buildings throughout Ontario.

Building Code Act, 1992

Under subsection 8(1) of the Building Code Act, 1992, no person shall construct or demolish a building, or cause a building to be constructed or demolished, unless a permit has been issued by the Chief Building Official.

Offences

Under the Building Code Act, 1992, a person may be guilty of an offence if they knowingly provide false information in an application, certificate, statement or return required under the Act or regulations; fail to comply with an order, direction or other requirement made under the Act; or contravene the Act, regulations or a by-law passed under section 7.

A Building Permit is a document that grants legal permission to undertake construction or other work regulated by the Ontario Building Code.

A Building Permit is required for:

  • Construction of a new building 10 square metres or greater
  • Construction of a designated structure listed in OBC 2024, Division A, 1.3.3.5
  • Placement of an existing building on a property
  • Erection of a tent or group of tents exceeding 60 square metres in area, or a tent attached to a building
  • Erection of an air-supported structure
  • Erection of a shelf and rack storage system
  • Construction of a public pool or spa
  • Renovation of an existing building or part of a building
  • Replacement, alteration, extension or repair of a building system, including decks and ramps
  • Construction or replacement of a deck 24 inches above grade or a deck attached to a building
  • Construction or replacement of a deck that forms the primary entrance into a building
  • Plumbing work not located within a building

A Building Permit is not required for:

  • A storage shed that is accessory to the primary-use building, is 15 square metres or less, is one storey in height and does not contain plumbing
  • Finish flooring and painting
  • Installation of cabinets
  • Replacement of roof shingles and siding
  • Replacement of doors and windows where there is no change to the size of the opening
  • Electrical work. An Electrical Safety Authority (ESA) permit may be required

Although a Building Permit may not be required, your project must still comply with applicable zoning requirements.

Building Permit Process

Pre-Consultation

Staff of the Building Department are available to meet with you before you submit your application and can assist you in navigating the permitting process.

Application

Once you submit an application for a Building Permit, a Building Official will review the application to ensure the plans and construction details meet the requirements of the Ontario Building Code and applicable laws, as identified in OBC 2024, Division A, 1.4.1.3.

You can obtain an Application for a Building Permit by dropping by City Hall or view/print a copy of the application for a permit to construct or demolish.  

Application for a Permit to Construct or Demolish

A complete Building Permit application includes:

  • Completed application form
  • Waste Diversion Plan
  • Complete set of construction plans
  • Entrance Permit for the driveway
  • Connection to Services Permit
  • Septic Permit, if municipal services are unavailable at the building site
  • Payment of the Building Permit fee

Additional documents may also be required, including:

  • Letter of authorization if the application is submitted by an authorized agent of the owner
  • Designs prepared by an Engineer or Architect must be signed and stamped accordingly
  • Designs prepared by a BCIN Designer must be accompanied by Schedule 1
  • Engineer/Architect commitment letter where professional design and review are required under OBC 2024, Division C

A complete set of construction plans must provide sufficient information to demonstrate compliance with the Ontario Building Code and applicable requirements. Depending on the project, plans may include the following:

Lot Plan

  • Property lines and total area of the property
  • Location of all existing and proposed buildings, including building type and footprint size
  • Location of streets, driveway, easements, rights-of-way, wells, septic tank, septic bed and overhead hydro lines
  • Setbacks between buildings and from buildings to property lines
  • Location of the nearest fire hydrant

Foundation Plan

  • Location and size of strip, pier and stepped footings
  • Location, size and spacing of reinforcing steel
  • Size and height of foundation walls
  • Type of ICF blocks, where used

Architectural Floor Plans

  • Room dimensions and ceiling heights
  • Room labels, such as bedroom and bathroom
  • Location of stairs, doors and windows
  • Location of fireplaces or wood stoves
  • Location of all smoke and carbon monoxide alarms

Structural Floor Plans

  • Location, size and spacing of supporting columns
  • Location, size and span of supporting beams, including specifications for engineered beams
  • Type, size and spacing of floor joists, including layouts for engineered joists
  • Type, size and spacing of wall studs
  • Type, size, spacing and pitch of roof rafters or trusses, including sealed specifications and layouts where applicable

Elevations and Cross-Sections

  • North, south, east and west elevations
  • Top of foundation elevation
  • Elevation of each floor
  • Roof peak elevation
  • Cross-sections showing the components of foundations, floors, exterior walls, interior walls and ceiling/roof assemblies

Construction Notes

  • Engineered beam and post connections
  • Deck and stair details
  • Required testing

Door and Window Schedule

  • Size and type of unit
  • Header size and minimum end bearing
  • Energy efficiency and fire rating

Surface Drainage Plan

  • Elevations affecting surface water drainage
  • Direction of water flow over the property
  • Location of storm drains or swales

Additional Documents

  • Engineer reports
  • Test results
  • Shop drawings

HVAC Package

  • Heat loss/gain report
  • Equipment specifications
  • Duct sizing and layout
  • Hydronic piping layout and manifold location

Other Permit Types

A Demolition Permit grants legal permission to demolish and remove a building or part of a building.

A complete Demolition Permit application includes:

  • Completed application
  • Letter identifying whether hazardous materials are present within the structure
  • Letter describing the demolition methodology to be used

Note: Demolition of large, tall or complex buildings may require supervision by engineers.

A Change of Use Permit grants legal permission to change the occupancy classification or use of a building.

Certain changes that increase the building's hazard index or increase occupant load by more than 15% may result in additional construction requirements.

An Occupancy Permit grants legal permission to occupy and use a building in the manner and for the purpose for which it was constructed.

An occupancy inspection must be conducted to ensure all requirements for occupancy have been met. If all requirements are satisfied, an Occupancy Permit will be issued by the Chief Building Official.

Except in the case of a swimming pool fence, no permit is required for the construction of a fence. No person shall construct a fence that does not comply with the requirements of By-law No. 2013-183. 

By-law No. 2013-183 - Regulate Fences 

Swimming Pool Fence Application 

Building Permit Fees

The fee structure for each type of permit and other Building Department services is provided in Appendix "A" of Schedule "A" of the applicable Building By-law.

Building Permit application fees are set by Council and reviewed annually. Fees are based on the value of construction, including materials, labour, design costs and special equipment. The value of land and landscaping is not included.

Current Building Permit fees are available in the City's By-laws section under By-law No. 2019-163.

Permit 

Once you submit all of the required information the "complete" application is approved and the building official issues the Building Permit. Staff will call or email you to let you know when your Building Permit is ready for you to pick up.

Type of Project Review Period
Residential projects under Part 9 10 working days
Commercial buildings and farm buildings under 600 m² 15 working days
Large buildings exceeding 600 m² 20 working days
Post-disaster buildings and complex buildings 30 working days

The applicable review period begins on the day after a complete application is received.

Please note: Within the applicable review period, the Chief Building Official will issue the Building Permit or advise the applicant in writing why a permit cannot be issued.

Construction may begin once your Building Permit has been issued.

Your project must be constructed in accordance with the plans certified by the Chief Building Official.

The Building Code requires the Building Permit to be posted in a window or other prominent location at the construction site. A copy of the building plans and specifications must also remain available at the site.

Changes proposed after a permit has been issued must be reviewed by the designer of record and approved by an inspector before changes are made to the certified plans.

Required Inspections

Each major phase of construction must be inspected by a Building Official to confirm that the work complies with the Ontario Building Code, Building Permit and approved plans.

The mandatory inspections applicable to your project will be identified on the Building Permit.

Important: Work must not be covered until it has been inspected and approved by a municipal Building Inspector.

Arranging an Inspection

It is the responsibility of the permit holder to notify the Building Department when work is ready for inspection at each required stage and before proceeding to the next stage of construction.

The inspector will complete the inspection within 48 hours, beginning the day after notice is received.

If work is covered before the required notice and municipal inspection have occurred, an order to uncover may be issued so that the work can be inspected.

This should replace the current website wording about officials being "generally able" to inspect with 24 hours notice.

Building Department Contact

Building Department Contact

Mel Bursey

Chief Building Official

Phone: 705-672-3363 ext. 4131

Email: mbursey@temiskamingshores.ca

Gabriel Tasse

Building Official / By-law Officer

Phone: 705-672-3363 ext. 4133

Email: gtasse@temiskamingshores.ca

Property Standards

To regulate property standards for property within the municipality. 

Please contact the By-Law Officer for information, questions or concerns.

Ken Ashik

By-law/Property Standards Officer

Phone: 705-672-3363 ext. 4135

Email: kashick@temiskamingshores.ca

Tips - Exterior Maintenance

All properties must be maintained in a neat and orderly fashion, and may not exhibit an unsightly appearance in comparison to adjacent property.

View or print a copy of the below information sheets.

Sign up to our Newsletter

Stay up to date on the city's activities, events, programs and operations by subscribing to our eNewsletters.